RAFINERY AND PETROCHEMICAL PLANT PROJECTS
Commencement | Completion | Project Name | Scope of the Project |
---|---|---|---|
2016 | ONGOING | T2240 STAR RAFINERY PROJECT/ ALİAĞA, TURKEY PIPE INSTALLATION WORKS |
Within the scope of this project; between 2" - 32" dia. 6.194 ton (274.000 WDI), <2" dia. 218 ton (81.000 WDI) pipe installation and in total 515 ton pipe support installation was completed. |
2013 | 2014 | TÜPRAŞ RUP PROJECT/ KOCAELİ, TURKEY PIPE SPOOL FABRICATION |
Within the scope of this project, 114,000 WDI carbon steel pipe spools were fabricated. |
2012 | 2013 | SOUTH YOLOTEN GAS FIELD DEVELOPMENT PROJECT-PACKAGE 2/ TURKMENISTAN PIPE INSTALLATION |
Within the scope of this project, 150.000 WDI process piping installation was completed. |
2011 | 2011 | LUHAIS & SUBBA OIL FIELD/ IRAQ MANİFOLD FABRICATION |
Within the scope of this project, 100 ton of manifolds were fabricated to be used at Luhais and Sabba Oil Field. |
2010 | 2012 | ASAB MAIN OIL LINE/ ABU DHABI, UAE PIPE INSTALLATION |
Within the scope of this project, 10.000 ton steel erection and 151.000 WDI pipe installation were completed. |
2008 | 2008 | KHURAIS WATER INJECTION PLANT/ SAUDI ARABIA PIPE SPOOL FABRICATION |
Within the scope of this project, total of 70,000 WDI pipe spools were fabricated. |
2006 | 2008 | KASHAGAN POWER PLANT/ KAZAKHSTAN PIPE SPOOL FABRICATION |
Within the scope of this project, total of 270,000 WDI pipe spools were fabricated. |